Rio Tinto to start underground mining at Kennecott copper operations


27 September 2022

Rio Tinto has approved a $55 million[1] investment in development capital to start underground mining and expand production at its Kennecott copper operations in Utah, United States.

Underground mining will initially focus on an area known as the Lower Commercial Skarn (LCS), which will deliver a total of around 30kt[2] of additional high quality mined copper through the period to 2027 alongside open cut operations. The first ore is expected to be produced in early 2023, with full production in the second half of the year. It will be processed through the existing facilities at Kennecott, one of only two operating copper smelters in the United States.

Kennecott holds the potential for significant and attractive underground development. The LCS is the first step towards this, with a Mineral Resource of 7.5 Mt at 1.9% copper, 0.84 g/t gold, 11.26 g/t silver, and 0.015% molybdenum identified based on drilling and a Probable Ore Reserve of 1.7 Mt at 1.9% copper, 0.71 g/t gold, 10.07 g/t silver, and 0.044% molybdenum[3].

Underground battery electric vehicles are currently being trialled at Kennecott to improve employee health and safety, increase productivity and reduce carbon emissions from future underground mining fleets. A battery electric haul truck and loader supplied by Sandvik Mining and Rock Solutions are being used to evaluate performance and suitability as part of underground development work.

Rio Tinto Copper chief executive Bold Baatar said, “This investment will allow us to quickly bring additional volumes of high quality copper to the market and build our knowledge and capabilities as we evaluate larger scale underground mining at Kennecott. We are progressing a range of options for a significant resource that is yet to be developed at Kennecott, which could extend our supply of copper and other critical materials needed for electric vehicles and renewable power technologies.

“Trialling underground battery electric vehicles is an exciting step in our work to create a safer workplace for our employees, increase the productivity of the mine and reduce emissions from our operations. We look forward to seeing their potential for deployment.”

Existing undergound infrastructure is currently being extended to enable early access to the next underground resource and undertake characterisation studies. A Feasibility Study to inform decisions on the next phase of underground production is expected to be completed in 2023. This will be one of several potential stages currently being investigated.

Feasibility studies are also being progressed to extend open pit mining at Kennecott beyond 2032.

The Table 1 Release was made in accordance with the JORC Code and the ASX Listing Rules. Mineral Resources are reported in addition to Ore Reserves. Mineral Resources and Ore Reserves are quoted on a 100 per cent basis.

A copy of the Table 1 Release is available on Rio Tinto's website at riotinto.com/invest/financial-news-performance/resources-and-reserves

 

 

(1) All dollar values are in USD.

(2) Lower Commercial Skarn production targets referred to in this release are reported as recoverable copper and are underpinned as to 100% by Probable Ore Reserves. These estimates of Ore Reserves were reported in a release to the Australian Securities Exchange (ASX) dated 31 August 2022 “Rio Tinto Kennecott Mineral Resources and Ore Reserves” (Table 1 Release) and have been prepared by Competent Persons in accordance with the requirements of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves, 2012 (JORC Code).

(3) The Mineral Resource and Ore Reserve estimates referred to in this release were set out in the Table 1 Release. The Competent Person responsible for the information in that release that relates to Mineral Resources is Mr Ryan Hayes, a Member of the Australasian Institute of Mining and Metallurgy (MAusIMM). The Competent Person responsible for the information in that release that relates to Ore Reserves is Mr Stephen McInerney, a Member of the Australasian Institute of Mining and Metallurgy (MAusIMM). Rio Tinto confirms that it is not aware of any new information or data that materially affects the information included in the Table 1 Release, that all material assumptions and technical parameters underpinning the estimates in the Table 1 Release continue to apply and have not materially changed, and that the form and context in which the Competent Persons’ findings are presented have not been materially modified.

 

This announcement is authorised for release to the market by Steve Allen, Rio Tinto’s Group Company Secretary.

riotinto.com

Please direct all enquiries to media.enquiries@riotinto.com

Media Relations, UK
Illtud Harri
M +44 7920 503 600

Matthew Klar
M+ 44 7796 630 637

David Outhwaite
M +44 7787 597 493

Media Relations, Americas
Simon Letendre
M +514 796 4973

Malika Cherry
M +1 418 592 7293

Investor Relations, UK
Menno Sanderse
M: +44 7825 195 178

David Ovington
M +44 7920 010 978

Clare Peever
M +44 7788 967 877

Media Relations, Australia
Jonathan Rose
M +61 447 028 913

Matt Chambers
M +61 433 525 739

Jesse Riseborough
M +61 436 653 412

Investor Relations, Australia
Tom Gallop
M +61 439 353 948

Amar Jambaa
M +61 472 865 948

Rio Tinto plc
6 St James’s Square
London SW1Y 4AD
United Kingdom
T +44 20 7781 2000
Registered in England
No. 719885

Rio Tinto Limited
Level 43, 120 Collins Street
Melbourne 3000
Australia
T +61 3 9283 3333
Registered in Australia
ABN 96 004 458 404

Category: Kennecott

Source: Rio Tinto